Manheim Central Construction Blog

  • Construction Blog Update October 2, 2018

    Posted by Marcie Elbin on 10/2/2018 2:45:00 PM

    Since the last update, we are happy to share that the playground equipment has arrived at Baron Elementary! The playground area is being prepared and footers will soon be installed. Once the area is prepared, district maintenance staff will assemble the equipment.

    The masons have completed their work on the building for now. Curbs and sidewalks are on the schedule to be poured this week and excavation is nearly complete for the parking lot on the North Linden Street side of the building.

    Work on the gymnasium is nearing completion, and seating and stairs are going in in the Large Group Instruction area. Glass installation on the exterior of the school, HVAC, boiler room, roof work are all nearing completion and installation of vents and drains in restrooms and sewer line work are finished.

    Casework cabinets are being worked on in Area C on both the first and second floors. Tiling of the walls and floors in bathrooms in all building areas, ceiling grid installation, insulation work, domestic water hook up in large restrooms, work in the school’s kitchen, and preparations for the installation of the electrical transformer are all on going.

    Comments (-1)
  • Construction Blog Update August 30, 2018

    Posted by Marcie Elbin on 8/30/2018 2:00:00 PM

    At their meeting on Monday, August 27, 2018, the Manheim Central School District Board of Directors approved the name of the new school:  Baron Elementary School.

    Many thanks to all who took time to participate in the school naming survey!

    __________________________________________________________________________________

    The removal of curbing on Gramby Street has occurred recently in preparation for grading of that area for the bus lane.

    Brick veneer is complete on 90% of the building and should be complete in approximately two weeks. It is expected that the building envelope will be complete near mid-September.

    Floors in Area C are being prepped for terrazzo, the installation of glass throughout the building is ongoing, and painting has begun in the gym.

    Piping and duct work connection is moving along. In Area A, water piping is 70% complete; Area B piping is 95% complete and ventilation duct work is complete; Area C piping is 95% complete and duct work is 90% complete. Water piping in the basement of the building is complete. In the kitchen, work is being done for the hood duct and fire suppression system.

    Cable tray installation continues throughout the building and permanent electrical power should be available in the next two weeks.

    Pictures below include:

    1. Cafeteria
    2. Gym
    3. Kitchen
    4. Large Group Instruction
    5. Loading Dock
    6. Media Center
    7. Rear of Gym

    Cafeteria Gym Kitchen Large Group Instruction Loading Dock Media Center Rear of Gym

    Comments (-1)
  • Construction Blog Update July 24, 2018

    Posted by Marcie Elbin on 7/24/2018 3:45:00 PM

    Since the last update, the brick work on the outside of the building is 50% complete, and the window installation is now 50% complete as well. 

    Footers for the outside canopy are 100% complete, and the canopy installation is upcoming.

    Interior block for the classrooms walls is 90% complete and block laying for the gymnasium is underway.

    Interior walls of Areas A (building offices, kitchen and cafeteria) & B (art and music areas and media center) are painted.

    The building chiller has been set on the roof of the building and mechanical equipment is being set up.

    Piping is finished to all main water lines and water meter hook up is occurring.

    Gas lines are being installed in to and throughout the building, and the electrical conduit is nearing completion in Areas B & C (classrooms).

     

    Updated pictures of the progress soon to come!

    Comments (-1)
  • Construction Blog Update June 28, 2018

    Posted by Marcie Elbin on 6/28/2018 2:25:00 PM

    Construction is moving right along!

    Brick work is ongoing around the outside of the school with Area C being complete.

    Dry walling has begun inside the building in the classroom and administration areas, and glass installation has begun on both floors of Areas A, B, and C with installation in the media center nearly finished.

    Plumbing in area A is 95% complete and fire protection is approximately 50% finished in areas A, B and C. Duct work and piping for the HVAC system is also about 50% complete in Areas A, B and C. The main water lines in the building are complete and wiring is beginning to take place in Area C.

    The gymnasium area will soon be closed off and preparation for the canopy that will run along the building on the Gramby Street side is ongoing.

    Roofing on the school is nearing completion with the area over the gymnasium still to do.

    Pictures below include:

    1. Media Center – Hazel St. view
    2. C Wing on Hazel St.
    3. Media Center – Gramby St. view
    4. Main entrance on Gramby St.
    5. Back view of Area C and gymnasium
    6. Loading dock
    7. Student/Staff entrance and kitchen

    Media Center on Hazel St C Wing on Hazel St Media Center on Gramby St Main Entrance on Gramby St Back of C and Gym Loading Dock Student and Staff Entrance and Kitchen

    Comments (-1)
  • Construction Blog Update May 24, 2018

    Posted by Marcie Elbin on 5/24/2018 9:00:00 AM

    Progress continues at the Gramby Street construction site:

    The roof is now complete on Area B and C wings and about 80% complete on Area A wing.

    The installation of mechanical components continues for Areas B and C. All of the concrete has been poured at this point except for the gymnasium floor, which will occur within the next week.

    Work continues to close in the kitchen area of the building, and concrete has been poured for the respective loading dock. Installation of insulation and electrical components is ongoing.

    Pictures below include: Rear view of Area C wing; Area C and gymnasium; staff entrance; main entrance; Area B wing; media center and front view of Area C wing.

    Rear of C Wing C and Gym Staff Entrance Main Entrance B Wing Media Center Front View C Wing

    Comments (-1)
  • Construction Blog Update April 10, 2018

    Posted by Marcie Elbin on 4/10/2018 11:45:00 AM

    We are happy to provide an update on the ongoing construction for the Gramby Street Elementary project!

     Site grading and installation of storm water structures are underway with the new sewer service piping and tamp complete. New electric service and communications service piping is installed, and with the completion of the relocation of the PPL pole, electric service lines are completed and moving the cable and phone wires is ongoing.

     Area A will be made up primarily of school offices, kitchen, and cafeteria. The cement block foundations are complete for this section and concrete has been poured. Structural steel is arriving on site and will start to go up on April 16th. In the basement section of Area A, foundation walls are 95% complete and basement walls have been poured. The mechanical/electrical pads are formed and poured.

     Area B of the building will contain the gymnasium, art and music areas, media center, large group instruction area and classrooms. The masonry block foundations are complete for this section. Structural steel is 90% complete in this area. The interior first floor masonry blocks (interior classroom walls and hallway walls) will start to go up early this week, and the second-floor slab of Area B is to be poured later in the week.

     Area C, the portion of the building that will house the majority of the classrooms, is coming along as well. Masonry block foundations, cement floor, and structural steel are complete. Block interior is 40% complete, roofing is 20% complete, and beam infill and parapet framing is 85% complete. The second-floor slab is to be poured early this week. The first and second floor mechanical/electrical component final connections, and the installation of electrical panel boards are all ongoing.

     The pictures below are of Areas A and B respectively.

    Area A Basement Excavation Area A Basement Steel Area A West Basement Area B Steel 1 Area B Steel 2 Area B Steel 3

    Comments (-1)
  • Construction Blog Update

    Posted by Caroline Duda on 10/24/2017

    The Gramby Street Elementary School Project is well underway.  The building is down, the basement is dug, basement footers are poured, and basement walls will be up and poured over the next couple of weeks. 

     

    Prior to the Board Meeting on Monday, October 23rd, the School Board visited the construction site for a groundbreaking photo, which is shown below.  Dan Bierzonski and Jim Martin, from EI Associates, joined us for the photo, as well as Fred Kendall, Construction Manager from Abacus Construction.  

     

    Please be aware that Gramby Street will be closed sporadically over the next few weeks between Hazel and Linden Streets in order to run water, sewer, and gas lines underground.  Please keep an eye on the Manheim Borough website for alternate routes. 

     

    Groundbreaking Group Photo

     

    Groundbreaking Group Pic Digging

     

    Groundbreaking Media Interviews

     

    Groundbreaking Sign on Site

    Comments (-1)
  • Construction Blog Update September 8, 2017

    Posted by Caroline Duda on 9/8/2017

    Demolition is underway at the Gramby Street site:

     

    Demolition of Gramby

     

    Demolition of Gramby

     

    Demolition of Gramby

     

    Comments (-1)
  • Construction Blog Update August 1, 2017

    Posted by Caroline Duda on 8/1/2017

    On Wednesday, July 26th, a community meeting was held at the District Office for residents that live close to the site of the Gramby Street building project.  Mr. Fred Kendall, Project manager, who also managed the Doe Run Elementary project, presented the project timeline and important demolition/construction information to residents.

     

    Timeline:

    Demolition is expected to begin sometime during the month of August and is expected to last approximately two months. It is anticipated that the total construction project will be completed by February of 2019.

     

    Demolition/Construction Information:

    The site will be secured with a locked fence (including the sidewalks), and equipment and material will be staged in the ballfield, also surrounded by fencing.  The streets will remain open and will only be closed on occasion for equipment movement. During demolition and construction there will be a few times residents may need to move their cars and there will be no parking.  The project manager will work with the police department to give sufficient notice.

    The hours of construction will be five days per week, 7:00 AM – 5:00 PM, with some circumstances when work may need to be done over the weekend, or equipment may come in earlier in the day (i.e. concrete, foundations, floors).

    This construction blog will be updated regularly throughout the project. We appreciate your patience and understanding throughout demolition and construction.

    Comments (-1)
  • Construction Blog Update April 3, 2017

    Posted by Caroline Duda on 4/3/2017

    The link below will enable you to view design information presented to the Board at the February 21, 2017 meeting.

     

    Gramby Street Elementary School Design

    Comments (-1)